Project Web App and Power BI Integration
Hi Paul_Mather ,
Sorry I should've clarified - I've tried to connect data using all the options, including the organizational account and it still can't authenticate:
UPDATE:
I've managed to connect the data for the Power BI web site through using the Project Web App PBI template, but only as it had the option under the organisational account to use OAuth. However I can't find this option on the Desktop app - when I'm signed into my normal account using the Organizational Account it still can't authenticate my credentials.
- Paul_MatherJun 14, 2022MVP
Hello BlissL ,
The Organizational account is correct but it looks like you are using the incorrect PWA URL as you have /default.aspx on the end? Enter the PWA Site Url without the /default.aspx for example:
https://tenant.sharepoint.com/sites/pwa
Paul
- BlissLJun 14, 2022Brass Contributor
Unfortunately still doesn't like to authenticate with the 'right' URL without the /default.aspx at the end.
Tried all levels to apply the settings to and no authentication
- tenant.sharepoint.com/
- tenant.sharepoint.com/sites
- tenant.sharepoint.com/sites/pwa
- Paul_MatherJun 15, 2022MVP
Hi BlissL ,
Does the account you're using having access to query the report API? In a web browser if you go to {pwaSite}/_api/ProjectData, for example https://tenant.sharepoint.com/sites/pwa/_api/ProjectData does you see the collections listed?
Paul