Forum Discussion
ITManuelBI
Jan 13, 2025Tin Contributor
Project web app- No up to date data via OData feed
Hi all, we are working with the project web app. The Data stored in the project web app is pulled via the OData feed connector into a PowerBI report. The project web app is hosted on https://compa...
ITManuelBI
Jan 14, 2025Tin Contributor
Hi RodFromm and Paul Mather
I have checked out, republished and checked in again all 34 projects, also the Templates and the Enterprise Global has been checked out, saved and checked in again.
Now it seems that i do get updated data ( looking at the "Lastpublished" date from the Projects table ) for some projects but not for all of them.
Paul_MatherHow can I check the endpoints directly? Looking directly in the PWA project center I can see the updated data ( looking at the "Lastpublished" date ), but not in the Projects table submited.