Project templates & connection to MS Teams Group

HI all,

 

I created a new project with the new MS Porject web client. Is it possible to use this project as a template that can be used for further projects with the same structure?

 

Also, I connected the "template" for testing purposes with a MS Teams group to see how I can assign tasks to a person - now I would like to remove the connection between the project and the Teams group is this possible? If yes, how can I do this?

 

Is it possible to assign tasks to any person in my organization or is it necessary that this person is in at least one group with me and is it also necessary that his person has a MS Project subscription?

 

Thanks in advance and best regards

Philipp

7 Replies

  • Lewis-H's avatar
    Lewis-H
    Iron Contributor

    Yes, it is possible to use Project templates for connecting to MS teams.

    • Philipp Dorn's avatar
      Philipp Dorn
      Copper Contributor
      Hi Lewis,

      how do I create Project templates for a MS Teams group that can be used by everyone?

      Thanks.
  • Naaser's avatar
    Naaser
    Copper Contributor

    Philipp Dorn 

    Hi Philip, Template and copying of a plan/schedule is not available in "Project for the web" yet.

    You may vote for the relevant idea in UserVoice though to push it to high priority of the dev team:

    https://microsoftproject.uservoice.com/forums/914203-project-for-the-web/suggestions/38916190-add-templates-to-project-for-the-web

     

    • Philipp Dorn's avatar
      Philipp Dorn
      Copper Contributor
      Hi Naaser,

      thanks for the info, I voted for this feature!

      Any idea about my other questions?

      Thanks
      • Naaser's avatar
        Naaser
        Copper Contributor

        Philipp Dorn 

        You are welcome!

        You can assign tasks to any users who is available in O365 (or AD) and as soon as you add them they will be member of associated group. However, if they don't have license (Project Online) they won't be abale to see or update the task.

        Hope this will answer the question.

        Regards,

        Naser