Forum Discussion
vincenzopiscitelli
Nov 16, 2021Copper Contributor
project team member restrictions
Hi, in Project Web App, I would like to further limit the collaboration privileges of users belonging to a project so that these users cannot change the start and end dates of the activities. The i...
vincenzopiscitelli
Nov 16, 2021Copper Contributor
Hi Paul_Mather,
users update activities directly in PWA.
At the moment when users make updates on activities they are immediately saved to the project.
How can I make sure that activity updates are authorized before they are recorded on the project?
Thanks.
Vincenzo.
Paul_Mather
Nov 16, 2021MVP
Hello vincenzopiscitelli ,
So are the users editing the full project plan from the Schedule PDP in PWA? If so, I would go change the access model to prevent Team Members edit access to the projects (the default access model in PWA) then get users to update tasks from the /Tasks page in PWA: {pwaUrl}/Tasks.aspx
It looks like this (from my test system - not real projects!):
Paul