Forum Discussion
project team member restrictions
Hello vincenzopiscitelli ,
Where are users updating the tasks? On the /Tasks page in PWA? If so, any changes here need to be approved by the Status Manager so that Status Manager can just reject the task start / end date changes. As far as I know there is no way to stop users changing the start and end date of a task they are assigned to from the /Tasks page in PWA.
Paul
Hi Paul_Mather,
users update activities directly in PWA.
At the moment when users make updates on activities they are immediately saved to the project.
How can I make sure that activity updates are authorized before they are recorded on the project?
Thanks.
Vincenzo.
- Paul_MatherNov 16, 2021MVP
Hello vincenzopiscitelli ,
So are the users editing the full project plan from the Schedule PDP in PWA? If so, I would go change the access model to prevent Team Members edit access to the projects (the default access model in PWA) then get users to update tasks from the /Tasks page in PWA: {pwaUrl}/Tasks.aspx
It looks like this (from my test system - not real projects!):
Paul
- vincenzopiscitelliNov 16, 2021Copper Contributor
Hi Paul_Mather,
yes, users are currently editing the entire project plan.
Could you please tell me step by step how I can change this setting so that I can receive requests for approval of user task updates?
Thanks.Vincenzo.
- Paul_MatherNov 16, 2021MVP
Hello vincenzopiscitelli ,
Guiding you on what to change on the Permission model isn't going to be easy via the forums as ideally we'd need understand the exact permission model settings in place today. You will need to ensure Team Members do not have Save access to the projects. The default Team Members group / My Tasks category settings can be seen below:
Default My Tasks category:
The default Team Members group:
Here is a guide up updating project progress: https://support.microsoft.com/en-us/office/step-3-update-progress-ca5c3826-85bf-4a31-9351-3b83fd7c8fe0 also: https://support.microsoft.com/en-us/office/Collaborate-2ce5cddb-87da-42fe-9df3-fbe37c3c7afb#Category=Task_Progress
Hope that helps
Paul