Project tasks assigned to resource are listed under Tasks, but not listed in Timesheet
Hi, I have created a project, tasks and assigned it to resources. I have ensured that Tasks are published, not locked and Resources are committed. Tasks are listed under the Tasks of the resource. ...
- Nov 19, 2021
Hello Lingaraju_CH ,
Are the Timesheets set to be prepopulated with the current task assignments?
Setting here: {pwaUrl}/_layouts/15/pwa/Admin/TSSettings.aspx
Paul
Paul_Mather
Nov 19, 2021MVP
Hello Lingaraju_CH ,
Are the Timesheets set to be prepopulated with the current task assignments?
Setting here: {pwaUrl}/_layouts/15/pwa/Admin/TSSettings.aspx
Paul
Lingaraju_CH
Nov 25, 2021Copper Contributor