Project tasks assigned to resource are listed under Tasks, but not listed in Timesheet

Hi, I have created a project, tasks and assigned it to resources. I have ensured that Tasks are published, not locked and Resources are committed. Tasks are listed under the Tasks of the resource. ...
  • Paul_Mather's avatar
    Nov 19, 2021

    Hello Lingaraju_CH ,

    Are the Timesheets set to be prepopulated with the current task assignments?

     

    Setting here: {pwaUrl}/_layouts/15/pwa/Admin/TSSettings.aspx

    Paul