Project summary actual duration or % complete lower than those of the sub tasks
I have been tracking this schedule for a while. Just noticed that the % complete or the actual duration of the Project summary task is lower than those of the sub tasks. Why is this weird behavior ? ...
Ignacio_Martin
Jan 30, 2023Iron Contributor
Hello.
The %Complete of a summary task is calculated as previously mentioned:
100 x Sum of all actual subtask durations / Sum of all subtask durations
And your Actual Duration = % Complete x Duration /100
Taking into account that the Duration = Maximum Finish date - Minimum Start date, of all its subtasks, counting in the Project Calendar.
Certainly, the Actual Duration of a summary task is the value of a proportion, which shows an idea of its progress, but which should not be interpreted as elapsed time or real duration.
You can do the checks in the example above. The Duration 1, Duration 2 column displays the sums of the Duration and Actual Duration of the subtasks, respectively.
Regards.