Project Start-To-Finish multiple link

Hi All,   I have in my Gantt two task related to testing activities that could happens in different moments. I have a third task that represents the test bench setup and I want to schedule it in o...
  • Dale_HowardMVP's avatar
    Dec 21, 2021
    matteboz -

    The Test Bench Setup task should be the Predecessor task to both of the testing tasks. Set a Finish-to-Start dependency between the Test Bench Setup task and each of the testing tasks. Hope this helps.