Forum Discussion
matteboz
Dec 21, 2021Copper Contributor
Project Start-To-Finish multiple link
Hi All, I have in my Gantt two task related to testing activities that could happens in different moments. I have a third task that represents the test bench setup and I want to schedule it in o...
- Dec 21, 2021matteboz -
The Test Bench Setup task should be the Predecessor task to both of the testing tasks. Set a Finish-to-Start dependency between the Test Bench Setup task and each of the testing tasks. Hope this helps.
Dec 21, 2021
matteboz -
The Test Bench Setup task should be the Predecessor task to both of the testing tasks. Set a Finish-to-Start dependency between the Test Bench Setup task and each of the testing tasks. Hope this helps.
The Test Bench Setup task should be the Predecessor task to both of the testing tasks. Set a Finish-to-Start dependency between the Test Bench Setup task and each of the testing tasks. Hope this helps.
- mattebozDec 21, 2021Copper ContributorHi Dale,
Thank you for your support.
My problem was that simply setting as you suggest move the bench setup to the begging of the project. Set is as "as late as possible" definitely solve my issues!
Thank you,
Matteo- Dec 21, 2021Matteo --
You are more than welcome for the help, my friend!