Forum Discussion
pauleast
Feb 02, 2021Tin Contributor
project Site creation failure
Hi I get the attached error when trying to build a site from a template. This happens for all the templates in our library, new and old.
Paul_Mather
Feb 02, 2021MVP
Hello pauleast ,
What happens when the EPT is set to use the default "Project Site" template - does that work?
Paul
pauleast
Feb 03, 2021Tin Contributor
Paul_Mather we don't have a default one as in OOB from Microsoft as we have a custom build. What does seem to be happening is the failure of the site build doesn't happen when we create a project from 'new' whereas using our pipeline list does...this links list items to custom fields in the project details.
- Paul_MatherFeb 03, 2021MVP
Hi pauleast ,
As a test, can you set one EPT to use the OOB Project Site template and create a Project from the pipeline list to see if it repros there?
Paul
- pauleastFeb 05, 2021Tin Contributorwe don't have an OOB template:( do you know if this exists online and we can add?
- Paul_MatherFeb 05, 2021MVP
Hello pauleast ,
On the EPT in the Site Template option in Project Online, there will be "Project Site" - that is the OOB project site template.
Paul