Project Server when an admin opens a certain project it is opening in read-only mode

We have Project Server and one of my admins is experiencing an issue where he can't check out one of his projects, I had the same issue and was able to clear my cache, however he cleared his cache and the project is still opening as read only for him, but not for me.  I am not sure what else he should do at this time. 

6 Replies

  • Hello nmanus,

    If other users can successfully check out and edit this project, then it will be something local to this user or this user's device. Can this user edit this project in the PWA web interface?

    • nmanus's avatar
      nmanus
      Copper Contributor

      Yes, he can edit the project site, but not the schedule. 

      • Hello nmanus ,

        So from the project center in PWA, if the user clicks the project name, click the Schedule PDP, click the Task Tab then click Edit - does that work?

        Paul