Forum Discussion
Project Server Permissions: Project Team Read/Write Own Project and Read-Only Other Projects
Thank you for your quickly rely. Yes, we would like the former: team members can function like the project manager by updating the schedule, new tasks, updating enterprise customs fields, etc.
Mike_ProjNewb -- Wow, asking team members to perform the duties of project managers is definitely NOT a good idea, but if that is what you need, so be it. I would begin the security process by simply adding your team members to the built-in Project Managers security group in PWA. Also, I would STRONGLY recommend that you get a Project Plan 3 license for each of your team members so that they can download and use Microsoft Project with Project Online. The built-in PWA functionality for managing a project is very limited compared to the power and flexibility in Microsoft Project. Hope this helps.
- Mike_ProjNewbJan 25, 2021Copper Contributor
Dale_HowardMVP
Hi Dale,
Yes, the "team members" are basically supervisors that can fill-in in the event of a sick project manager, pregnancy, etc. All of the project managers and team members have Project Pro desktop software installed and able to connect to the PWA - so I know we have the correct license (sorry I don't know the license name, my IT department takes care of it).
When adding users to the Project Managers security group within PWA, do I accomplish this by simply browsing Settings -> Manage Groups -> Project Managers -> Add Users? If so, how does PWA differentiate some users being able to access some projects, while other users are able to access different projects?
Or do I adjust security groups (or sharepoint site permissions?) at the project level? If so, how do I accomplish this?
Thanks again for your help!- Jan 25, 2021
Mike_ProjNewb -- Yes, you have the right steps to add the team members to the Project managers security group. The system "figures out" which projects belong to which team member by using the My Projects category that is included in the Project Managers group. No, you should not need to change any other permissions to get this to work. Hope this helps.