Forum Discussion

Irene2023's avatar
Irene2023
Copper Contributor
Aug 29, 2023

Project Publish failed

Hello,

Please assist , recently when i publish in project web i got this error

 

 

 

Recently in ms project there is no option to publish project while it was there 

 

 

 

 

 

Error Message i got

 

Your ProjectPublish job failed. Its current state is FailedNotBlocking. It was 0 complete. It entered the queue at 08/29/2023 01:38:01.

The errors returned from the queue are as follows:
 Error ID: 23001
 Error ID: 23000
 Error ID: 26000

Detailed error below - send it to the administrator for more detailed troubleshooting.

<?xml version="1.0" encoding="utf-16"?> <errinfo> <general> <class name="Project"> <error id="23001" name="ProjectCurrencyConflict" uid="abd3845c-4746-ee11-a34b-005056aa30ae" /> </class> <class name="Microsoft.Office.Project.Server.BusinessLayer.Queue.Message"> <error id="23000" name="ProjectPublishFailure" uid="acd3845c-4746-ee11-a34b-005056aa30ae" projectuid="9a508f59-1b4a-ed11-8eec-f0d5bf656ebc" messagetype="Microsoft.Office.Project.Server.BusinessLayer.QueueMsg.CheckProjectCurrencyPolicyMessage" messageID="7" stage="" blocking="DontBlock" /> </class> <class name="Queue"> <error id="26000" name="GeneralQueueJobFailed" uid="add3845c-4746-ee11-a34b-005056aa30ae" JobUID="2fc26057-4746-ee11-a34b-005056aa30ae" ComputerName="ba1790e9-376b-4843-90e0-20bd234adca1" GroupType="ProjectPublish" MessageType="CheckProjectCurrencyPolicyMessage" MessageId="7" Stage="" CorrelationUID="e229d5a0-b015-205a-adca-112564b7e7e8" /> </class> </general> </errinfo>

You can do the following:
1. Try troubleshooting using the error IDs, error XML.
2. Contact administrator with your jobID (2fc26057-4746-ee11-a34b-005056aa30ae) and error XML.

 

 

Thanks,

 

 

 

 

2 Replies

  • Hello Irene2023 ,

    Have you got PWA set to enforce a certain currency like below:

     

    You / your admin can check this in PWA Settings > Additional Server Settings.

    Paul

    • AnnekeW's avatar
      AnnekeW
      Copper Contributor

      Hi! I have the same problem, but it started out with failed resource dummy's. Now I just have a whole list of the same project that I tried to save in various versions in the queue that all can't be processed. What to do?