Forum Discussion
Project progress not updating after approving timesheet
- Apr 17, 2020
Thanks khyron - are you able to mark the reply as the answer / best response so this will help others too?
Paul
Hello khyron,
Are you using single entry mode? On the PWA Settings page, check "Timesheet Settings and Default" settings, scroll to the bottom of the page and look for "Single Entry Mode". This means that the timesheet data will also create a Task Status update. Once this Task Status update is approved by the Task Status Manage into the project plan it will progress the task. More details around timesheets can be seen here: https://docs.microsoft.com/en-us/projectonline/set-up-timesheets
Paul
- khyronApr 17, 2020Brass Contributor
Thanks that did the trick Paul_Mather
- Paul_MatherApr 17, 2020MVP
Thanks khyron - are you able to mark the reply as the answer / best response so this will help others too?
Paul
- khyronApr 17, 2020Brass Contributor
Yes - sorry , I'm new here.
I think I clicked on the wrong reply as the best response