Project Professional task ID mixup across linked projects
Hi, Ran into a problem yesterday with a customer using linked projects (Master, subproject and a shared resource pool) Recently, when opening their masterfile they start getting "not able to link...
C_G_Hemmingsen
Jan 11, 2023Copper Contributor
John-project: Thank you very much for your feedback. I fear though, that designing the logic and coding it as a macro or an application to fix faulty task IDs may take longer than doing a manual rebuild, even if they have the dev skills.
Appreciate your offer on your existing macro. It sounds like a great tool, just maybe not for this particular situation.
John-project
Jan 12, 2023Silver Contributor
C_G_Hemmington,
Your correct, there is significant effort in developing a macro to ferret out faulty link structures and for a "one-off" it wouldn't make sense. My macro was designed for a different purpose and it might or might not be of much help in your situation.
Thanks for the feedback and good luck.
John
Your correct, there is significant effort in developing a macro to ferret out faulty link structures and for a "one-off" it wouldn't make sense. My macro was designed for a different purpose and it might or might not be of much help in your situation.
Thanks for the feedback and good luck.
John