Project Professional Issue Durations days not totalling correctly
Hi there, I am new to MSP and am setting up a schedule for a house boat build. Duration days are not adding up properly so could somoeone have a look at the screenshot and tell me what I am doing wr...
Ignacio_Martin
Aug 15, 2024Iron Contributor
Hi Mark
Try setting the duration of tasks ID: 31, 35 and 36 to 0 days, then write their previous durations: 4d, 6d and 6d and tell us what happened.
Ignacio
Try setting the duration of tasks ID: 31, 35 and 36 to 0 days, then write their previous durations: 4d, 6d and 6d and tell us what happened.
Ignacio
- MarkLoddingAug 20, 2024Copper Contributor
Thank you. I will give this a workaround and see how it goes. I will message back later in the week.