Forum Discussion

Mino_DC's avatar
Mino_DC
Copper Contributor
Sep 15, 2022
Solved

Project Pro 2021 - Add column with total resources number

I would like to add a column with the total number of resources in the Gantt view.
If I add 4 resources for a specific task, I would like to see in the column, the sum of the resources ... in this case, 4.

I tried this, but it didn't work:


I created 4 resources in the "Resource Sheet" and added the value 1 to the "Number 1" field and all 4 resources are in the same Group.
Next, in the Gantt view, I add the column with choice Number 1 and modified it, like so:

 
 

https://docs.microsoft.com/answers/storage/attachments/239762-image.png 




How can I do this?

Thanks all for any suggestions.

  • Mino_DC,
    You're welcome and thanks for the feedback. Obviously I wrote both macros, one counts all assignments while the other is focused on only work type resources. I'm glad you found the one that works for you.
    John

3 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    Mino_DC,
    The reason it didn't work for you is because the Resource Number1 field is not the same as the Task Number1 field. For reference, there are also two more Number1 fields, one for Task Assignments and one for Resource Assignments.

    This same question came up a while back and I wrote the macro.
    John
    Sub ResCountPlus()
    'This macro writes the number of task assignments into Text1
    ' and writes the number of working days for each task into Text2
    Dim t As Task
    For Each t In ActiveProject.Tasks
    If Not t Is Nothing Then
    If t.Assignments.Count > 0 Then
    t.Text2 = t.Assignments.Count
    End If
    t.Text1 = Format(t.Duration / 60 / ActiveProject.HoursPerDay, "##") & " days"
    End If
    Next t
    End Sub
    • Mino_DC's avatar
      Mino_DC
      Copper Contributor

      HiJohn-project  thanks for your reply.

      With this macro I not obtain that I would like.

      Based on your description, I found this article:

      https://answers.microsoft.com/en-us/msoffice/forum/all/microsoft-project-counting-total-resources-in-a/8513f5e4-96ce-4cc1-b007-8465a44246b4

       

      where you have written this solution:

      Sub CountWorkRes()
      Dim t As Task
      Dim a As Assignment
      Dim i As Integer
      For Each t In ActiveProject.Tasks
      i = 0
      If Not t Is Nothing Then
      For Each a In t.Assignments
      If a.ResourceType = pjResourceTypeWork Then i = i + 1
      Next a
      t.Number1 = i
      End If
      Next t
      End Sub

       

      I added a Number1 column in Gantt view and next run macro.

      This Macro works for me....

       

      Thanks

      • John-project's avatar
        John-project
        Silver Contributor
        Mino_DC,
        You're welcome and thanks for the feedback. Obviously I wrote both macros, one counts all assignments while the other is focused on only work type resources. I'm glad you found the one that works for you.
        John