project plan updates in project online

Hi I am currently using the desktop client version to prepare and update the project plan. Once i have completed the updates, i would like to save the updated plan in Project Online. I am not sure h...
  • Dale_HowardMVP's avatar
    Dale_HowardMVP
    Sep 06, 2022
    Robert --

    Tell your IT admin to specify the Project Permissions mode in Project Online after the instance is set up, and then to add you to the Project Managers security group. He/she will need to perform those two actions before you will be able to use Project Online. Hope this additional info helps.