Forum Discussion
robertpoddar
Aug 24, 2022Tin Contributor
project plan updates in project online
Hi I am currently using the desktop client version to prepare and update the project plan. Once i have completed the updates, i would like to save the updated plan in Project Online. I am not sure h...
- Sep 06, 2022Robert --
Tell your IT admin to specify the Project Permissions mode in Project Online after the instance is set up, and then to add you to the Project Managers security group. He/she will need to perform those two actions before you will be able to use Project Online. Hope this additional info helps.
robertpoddar
Aug 24, 2022Tin Contributor
I think i found the solution, but i am not 100% sure if this is the right way. I went to Sharepoint and clicked on the icon next to the project name. The project plan opened in the Desktop.. i guess if i now make changes to the plan and save it, it should get saved in Sharepoint.
- Aug 24, 2022robertpoddar --
Saving your project MPP file in SharePoint is NOT the same as saving it in Project Online. Read my previous reply for the correct way to do this. Hope this helps.