Project Plan 5 Vs Project Plan 3
Hello, I currently have Project Plan 3 installed and my colleague has Project Plan 5? What features are added in Microsoft Project for my colleague who has Project Plan 5? How can my colleagu...
Steve2325
Aug 25, 2022Copper Contributor
Are there any videos or documentation to show how to use the Portfolio Analysis tool in MS Project?
Aug 25, 2022
Steve --
The Portfolio Analysis tool in Project Online and Microsoft Project Server is a VERY sophisticated tool, and is intended for organizations that want to optimize their project intake process. Microsoft has developed some fairly good documentation on this tool at:
https://docs.microsoft.com/en-us/projectonline/portfolio-analysis-overview
In their web site, be sure to read all of the articles related to this topic, including how to set up the tool. Also, if you do a Google search for "Portfolio Analysis tool in Project Server", you will find multiple links to YouTube videos on the subject. I have not watched any of these videos personally, so I cannot recommend any of them for you.
Hope this helps.
The Portfolio Analysis tool in Project Online and Microsoft Project Server is a VERY sophisticated tool, and is intended for organizations that want to optimize their project intake process. Microsoft has developed some fairly good documentation on this tool at:
https://docs.microsoft.com/en-us/projectonline/portfolio-analysis-overview
In their web site, be sure to read all of the articles related to this topic, including how to set up the tool. Also, if you do a Google search for "Portfolio Analysis tool in Project Server", you will find multiple links to YouTube videos on the subject. I have not watched any of these videos personally, so I cannot recommend any of them for you.
Hope this helps.