Forum Discussion
fbcarvalho2020
May 29, 2024Tin Contributor
Project Plan 3 license usage
Hi, I'd like to know if it is possible to identify users with Project Plan 3 licenses who aren't using it. I have more than 3k Project Plan 3 licenses, but I'm not sure if all of them are bei...
- May 29, 2024
fbcarvalho2020 I recently developed a report to accomplish what you're after for Essentials and Plan 1/3/5 licenses. It's not perfect, but your options are limited. I used Power BI to connect/combine the data listed below. This is just an overview but should give you some ideas on how to accomplish what you're trying to do.
- Use the report Paul referenced.
- Audit Purview - Go here Audit - Microsoft Purview. Have your global SharePoint Admin run page view queries against specific pages within each PWA site. For example, Project Managers would normally access the https://<PWA URL>/Projects.aspx and https://<PWA URL>/Resources.aspx pages within a PWA. This report included a separate row with user info and date/timestamp that they accessed the page.
- Get a list of email addresses with assigned MSP license.
- Connect to PWA and retrieve list of MSP resource email addresses and whether they are active
- Connect to PWA and retrieve users email address assigned to the Project Managers (Project Web App Synchronized) group or any custom groups you have that Plan 3 licensed users would be assigned.
Paul_Mather
May 29, 2024MVP
Hello fbcarvalho2020 ,
The only report / usage details you have can be seen here: https://learn.microsoft.com/en-us/microsoft-365/admin/activity-reports/project-activity?view=o365-worldwide
Paul
fbcarvalho2020
May 29, 2024Tin Contributor
Thank you Paul. This report is not enough for me.