Project Permission for program Managers

Project server 2019  with Project Permissions Mode Is it possible to build a project permission for a group to have View only access to project schedule but they can update the SharePoint list such ...
  • Paul_Mather's avatar
    Feb 19, 2023

    Hello Ana-S ,

    The view only access to all projects in PWA and all project sites in PWA is simple enough, the default "Portfolio Viewers" group will give you that. The edit access to the Issues and Risks lists is based on the below:

    Without giving "Program Managers" Manage SharePoint Foundation permission or Save Project permission to all projects, you'd have to ensure all program managers were assigned to a task in every project.

    Paul