Forum Discussion

JeanLouis's avatar
JeanLouis
Copper Contributor
Sep 24, 2019
Solved

Project Online %work and actual cost ERROR

Hi All,   I start pulling out my hairs! When manipulating a schedule with Project Online, it happens quite often that the %work starts not working at all. The summary tasks don't populate the %wor...
  • JeanLouis's avatar
    JeanLouis
    Sep 25, 2019

    Hi,

     

    As you were asking the question, I thought trying other columns as well.

    The [work} value remains at 0, but if  I use th [% complete] column instead of the [% work complete], it works !

    What is the difference between the 2 columns ??

     

    Thanks a lot

    JL