Forum Discussion

TamaraF's avatar
TamaraF
Brass Contributor
Feb 15, 2024
Solved

Project Online Project Site - Adapt left hand navigation

Hi there, we created a new Project Site template based on the default Project Site Template and altered the left hand navigation (removed unused lists, added links to lists with other endpoints). Ho...
  • TamaraF's avatar
    TamaraF
    Feb 15, 2024

    Paul_Mather Thanks for your reply. However, I knew we never solved this programmatically, so I searched for an alternative. Your hint concerning the provisioning process lead me to the answer.

     

    You need to activate the Project Web App Connectivity site feature beforehand on the site. Then the default Project lists are already created and the navigation entries are created. Now, you can delete the Navigation entries (or move them around) and save your template. During provisioning of new projects the new navigation will be kept.

     

    This does not break the provisioning process (as long as you don't touch the lists themselves of course) and you can adapt the navigation without the process interfering.