Forum Discussion
Matthew Russell
Nov 08, 2022Copper Contributor
Project Online overwriting my calendar when uploading
Hi I hope someone can help I am having an issue when uploading a new project from the desktop to project online. The main base calendar for the system does not have any exceptions, as we are a glo...
Nov 08, 2022
Matthew --
It sounds like you are a Project Online administrator since you were able to add the calendar as an enterprise calendar. Regarding the resources in this project, as the administrator, did you actually check out these resources for editing from the Resource Center page in PWA and then specify their Base Calendar value there? If you only changed this in the project itself, the resources will always revert back to their settings in the Enterprise Resource Pool. Please let us know and we will try to help you.
It sounds like you are a Project Online administrator since you were able to add the calendar as an enterprise calendar. Regarding the resources in this project, as the administrator, did you actually check out these resources for editing from the Resource Center page in PWA and then specify their Base Calendar value there? If you only changed this in the project itself, the resources will always revert back to their settings in the Enterprise Resource Pool. Please let us know and we will try to help you.
Matthew Russell
Nov 09, 2022Copper Contributor
Hi Dale
Thanks for the swift reply
I didnt check out the resources, only changed it in the resource step of the upload wizard.
If I change it in the online resource it will change all other projects they are assigned to wont it? As this is a one off is there a way to upload but to only use the project calendar rather than the resource calendar?
Thanks for your help
Matt
- Nov 09, 2022Matt --
OK, I located the source of your problem. No, there is not a "one off" method to resolve your calendar problem. Sorry, but hope this helps.- Matthew RussellNov 11, 2022Copper Contributor
OK thank you.
Is there a way round this then? Id actually prefer the system to always take the project / work hours calendar over the resources calendar when we upload. So happy to change a setting to make this happen as a permanent thing if its possibleThanks
Matt
- Nov 11, 2022Matthew --
The only workaround of which I can think is to manually change the Base Calendar value in the Resource Sheet view for each of your project's resources. You would need to do this every time you open your enterprise project. You could probably write a macro in VBA to automate the process. But, as I stated earlier, there is no way for a project manager to permanently change any values for enterprise resources in the actual enterprise project. This has been a limitation of both Project Server and Project Online for a very long time. Sorry, but hope this helps.