Forum Discussion
Matthew Russell
Nov 08, 2022Copper Contributor
Project Online overwriting my calendar when uploading
Hi I hope someone can help I am having an issue when uploading a new project from the desktop to project online. The main base calendar for the system does not have any exceptions, as we are a glo...
Nov 08, 2022
Matthew --
It sounds like you are a Project Online administrator since you were able to add the calendar as an enterprise calendar. Regarding the resources in this project, as the administrator, did you actually check out these resources for editing from the Resource Center page in PWA and then specify their Base Calendar value there? If you only changed this in the project itself, the resources will always revert back to their settings in the Enterprise Resource Pool. Please let us know and we will try to help you.
It sounds like you are a Project Online administrator since you were able to add the calendar as an enterprise calendar. Regarding the resources in this project, as the administrator, did you actually check out these resources for editing from the Resource Center page in PWA and then specify their Base Calendar value there? If you only changed this in the project itself, the resources will always revert back to their settings in the Enterprise Resource Pool. Please let us know and we will try to help you.
- Matthew RussellNov 09, 2022Copper Contributor
Hi Dale
Thanks for the swift reply
I didnt check out the resources, only changed it in the resource step of the upload wizard.
If I change it in the online resource it will change all other projects they are assigned to wont it? As this is a one off is there a way to upload but to only use the project calendar rather than the resource calendar?
Thanks for your help
Matt
- Nov 09, 2022Matt --
OK, I located the source of your problem. No, there is not a "one off" method to resolve your calendar problem. Sorry, but hope this helps.- Matthew RussellNov 11, 2022Copper Contributor
OK thank you.
Is there a way round this then? Id actually prefer the system to always take the project / work hours calendar over the resources calendar when we upload. So happy to change a setting to make this happen as a permanent thing if its possibleThanks
Matt