Project online essentials supporting subprojects?
As per the subject really, does Project Online Essentials support subprojects? thanks Dave
Trutz_Stephani
Aug 27, 2017Steel Contributor
Hi David, Project Essentials is to be used by people in the team member role. To manage projects you need at least the Project Professional subscription. This also allows to manage subprojects in the web. To setup master and sub projects you always need the Project desktop client.