Project Online / Desktop – Team Planner – display the name oft he task
Hello together - wish you all a happy day ! Hopes you can help me. We use MS Project Online (Plan5) with client Project Prof. 2016 Problem: I manage multible projects at the same time, when ...
Guillaume Rouyre
Jul 29, 2021Brass Contributor
If the other project is not opened, you cannot see the task name but only the project name. This is a security matter, the project manager of a project might not have the right to access any other projects. You'll note this is the same behavior in the resource usage view. For a give resource, you can see his assignment on the open project at task level, but the assignments on other projects are at project level.