Project Online - Replacing Generic resource with 2 named users through Resource Engagements

Hello All, I'm exploring Resource Engagement functionality for resource demand management in Project Online and have following scenario based questions related to the same: Scenario 1: PM has a ta...
  • Dale_HowardMVP's avatar
    May 19, 2022
    MayurPode --

    In both of your scenarios, you cannot use a single Generic resource. Instead of a single resource named Developer in your organization's Enterprise Resource Pool, your application administrator would need to create multiple instances of the Developer resource, named something like Developer 01, Developer 02, Developer 03, etc. In Scenario #1, when two developer resources are needed for a task, you would add two of the numbered Developer generic resources, such as Developer 01 and Developer 02, and then assign them to tasks. That way, each of the Developer resources could be replaced with a human (named) resource. In Scenario #2, you would add two of the numbered Developer resources, such as Developer 01 and Developer 02, and then create two Resource Engagements, one for each of the Developer resources.

    What you have described in your scenarios are situations I have encountered a number of times, and what I am sharing is my recommended best practice approach. Hope this helps.