Project Online - Project Owner is changing to another User automatically
Project Online - I have a project in PoL and the Owner is changing to a different user automatically. I will change it back to myself but then after a little time it will automatically change to anot...
Woody
Aug 08, 2023Brass Contributor
AaronDemenge This happened to me when one project had more than 1 user with write permissions when the project plans are overwritten from MS Project. If user A overwrites the plan from MS Project the Owner will became user A, same happens when user B overwrites the plan, user B becomes the Owner.
Let me know if this was your case.