Project Online - No Tasks Visible in Project Server
Hi there, I have prepared a few sample Project files in which I have created tasks and assigned the tasks to Resources (who have similar access using Project Online). When I assign the task to the ...
Dec 01, 2023
VU_09 --
Have you actually PUBLISHED this project? You must publish an enterprise project for the information in the project to become visible in PWA, particularly in the Project Center page, Tasks page, and the Timesheet page. To publish an enterprise project, click File > Info > Publish. Hope this helps.
Have you actually PUBLISHED this project? You must publish an enterprise project for the information in the project to become visible in PWA, particularly in the Project Center page, Tasks page, and the Timesheet page. To publish an enterprise project, click File > Info > Publish. Hope this helps.
- VU_09Dec 01, 2023Copper Contributor
Dale_HowardMVP Thank you for the prompt response! Yes I have published the project samples I had created, but have yet to see the resource assignments flow through to the Task view. Please find a quick view of the Projects tab below for your reference.
- Dec 01, 2023VU_09 --
Is the user an enterprise resource in the Enterprise Resource Pool in PWA? And if so, is the user a member of the Team Members group in PWA? Please let us know and we will try to help you.