Forum Discussion
dslusser
Feb 02, 2023Copper Contributor
Project Online - Hour Timeline
Hello, I am completely brand new to Project and am starting off with Plan 1 (found https://www.microsoft.com/en-us/microsoft-365/project/compare-microsoft-project-management-software?activetab=ta...
dslusser
Feb 03, 2023Copper Contributor
Does anyone know if upgrading to the $30/month Plan 2 will give me this option? It looks like it provides the desktop version, which I am assuming is the full blown version of MPP?
Feb 03, 2023
dslusser --
If you need to plan your project tasks in hours and then to display those tasks in hours in the Gantt Chart view, then yes, the Project Plan 3 option will provide you with the Microsoft Project desktop version. In the Gantt Chart view, you will be able to zoom the timescale to show the schedule of tasks in hours and not in days. Hope this helps.