Project Online - Error while approving Timesheet
- Apr 02, 2024
Hello ramkanumuri ,
Your best option is to open a support ticket with Microsoft via the M365 admin portal, Microsoft will then be able to review the ULS logs on the server to understand the data issue causing the problem.
Paul
Hello ramkanumuri ,
Your best option is to open a support ticket with Microsoft via the M365 admin portal, Microsoft will then be able to review the ULS logs on the server to understand the data issue causing the problem.
Paul
- BhatiaMar 25, 2025Copper Contributor
Hi Ramkanumuri: did opening a support ticket resolve your issue? I am asking this as I am also seeing the same error message. Thanks. AB
- BhatiaApr 23, 2025Copper Contributor
For those who encounter this, this is how I was able to resolve this. Had two Approvers/managers who were noticing this problem. I assigned them Portfolio Manager rights, in addition to Project Manager rights that they already had, and they were able to approve all the pending timesheets. [