Project Online - creation of resource groups
Hi all I have just started to look at Project Online and would like to ask for some help on the resources. I can see that you can see the capacity and utilisation for individual resources, but ...
- Jun 02, 2021
Hello scotthannaford1973 ,
Yes you can do this. Edit a resource and scroll down to the section "Team Details". You can create a Team so that the capacity is at the Team level rather than the individuals. Here is a good post: http://applepark.co.uk/working-with-teams-in-project-onlineproject-server-2013/
Paul
Paul_Mather
Jun 02, 2021MVP
Hello scotthannaford1973 ,
Yes you can do this. Edit a resource and scroll down to the section "Team Details". You can create a Team so that the capacity is at the Team level rather than the individuals. Here is a good post: http://applepark.co.uk/working-with-teams-in-project-onlineproject-server-2013/
Paul
scotthannaford1973
Jun 02, 2021Copper Contributor
much appreciated - have been struggling to find anything useful so that's fabulous.