Project Online - Capacity planning does not show project anymore when they are "Published"

Hi all,  I am experiencing a strange behavior from Project Online : since a couple of week, when i publish a project, the Resource Capacity planning (workload for a resource by project), for a given...
  • Laurent PIGEON's avatar
    Laurent PIGEON
    Dec 16, 2021
    Hi Paul,
    I finally had a fix by Microsoft Support : In the Server settings / Reporting, the "Never" option was selected. I understood this was responsible for not updating the database after updates in Project Pro or PWA.

    Once this option set to "Daily", the behavior was normal again.

    Thank you very much for your help !
    Laurent.