Project Online - Can remove finished tasks from resources' timesheet?
Hi, I am trying to use Project online and having trouble with timesheets. Can we remove completed tasks from resources' timesheet?? (Complete percentages are 100% and remaining hour is zero). ...
Joey_Cho
Feb 07, 2023Tin Contributor
Hi Dale Howard,
Thank you so much for your advice!
I have another relevant question want to ask.,
I have dozens of finished projects and thousands of task.
Is there any other way, I can remove all the tasks of finished projects?
Thanks !
Thank you so much for your advice!
I have another relevant question want to ask.,
I have dozens of finished projects and thousands of task.
Is there any other way, I can remove all the tasks of finished projects?
Thanks !
Feb 08, 2023
Joey --
The first question that comes to mind is, "Why do you need to do this?" If the need is somehow important, the solution would be to open every project, set the Publish value to No for every task, and then to publish the project. There is no shortcut to make it faster and easier.
So, my question remains, "Why do you need to do this?" Let us know. Thank!