Project Online - Approval for inclusion in the working group
Hello! I really hope for advice. Ours is used by Office 365 and Project Online. There is a task, it is necessary to make sure that when an employee is added to the project working group and tasks a...
Jan 17, 2023
dkozhemyak --
In Project for the Web (to which I believe you erroneously refer as Project Online), there is no functionality that allows a line manager or resource manager to approve resource assignments on tasks. On the other hand, if you were using Microsoft Project with Project Online, there IS functionality like this. It is known as the Resource Engagement feature. Hope this helps.
In Project for the Web (to which I believe you erroneously refer as Project Online), there is no functionality that allows a line manager or resource manager to approve resource assignments on tasks. On the other hand, if you were using Microsoft Project with Project Online, there IS functionality like this. It is known as the Resource Engagement feature. Hope this helps.