Project on Web - email notification to assigned team members
- Sep 11, 2023
Hello pndungu ,
You can build your own notifications fairly easily using Power Automate. You could start with this template and customise to what you need: https://powerautomate.microsoft.com/en-us/templates/details/a530fc4165b14f479dc07c3143bfb94c/daily-project-for-the-web-task-reminder/
Paul
We're trying to do the same thing with Project for Web. I was wondering about the below link though.
https://support.microsoft.com/en-us/office/get-email-reminders-about-your-work-in-project-web-app-2372c181-1c98-416a-9306-ac28f027334b#bkmk_personal
It looks like there are built in notifications for things like tasks starting soon, tasks ending soon, tasks changing status, etc. When we look at notification options though, we only see options to be notified when someone is added to a task or to a project/roadmap.
Is this feature not included in a Project Plan 1 subscription.
- RodFrommOct 13, 2023Steel Contributor