Forum Discussion
Matthew Russell
Jun 02, 2021Tin Contributor
Project level calculated custom field using project level cost
Hi All I am trying to create a project level enterprise custom field which is based on a formula. The formula I am trying to use is very simple - "project level cost field" / Cost The issue I am h...
- Jun 02, 2021
Hello Matthew Russell ,
You can type the name of the custom field, for example if the field is called "My custom project cost" type [My custom project cost] in the formula input box - including the brackets.
Paul
Paul_Mather
Jun 02, 2021MVP
Hello Matthew Russell ,
You can type the name of the custom field, for example if the field is called "My custom project cost" type [My custom project cost] in the formula input box - including the brackets.
Paul
Matthew Russell
Jun 03, 2021Tin Contributor
Hi Paul_Mather
Thank you very much, that worked great. I always assumed you had to use the ones in the list.
Thanks
Matt