Project Layout Configuration makes Baseline disppearing
When I UNSELECT the "Round bars to whole days" checkbox in the Layout form, the Baseline bars disappears in the Control Gantt view. What is happening?
carlosmoro
Jul 12, 2023Copper Contributor
Yes Dale !!
That's what I assume too. But in this case, how can we deal with it?
Regards
That's what I assume too. But in this case, how can we deal with it?
Regards
Jul 12, 2023
carlosmoro --
There is no workaround for this bug, as far as I can tell. The best I can offer you is that you should not deselect the "Round bars to whole days" checkbox in the Layout form. Sorry, but hope this helps.