Forum Discussion
ThePM-CA
Jun 27, 2022Brass Contributor
Project health indicators
Hi I am kind of struggling displaying graphics as project health indicators. I am able to display text without any problem. I have tried all steps to display icons but in vain I am the proj...
ThePM-CA
Jun 28, 2022Brass Contributor
Thank you Paul. I will certainly go through this. The text status which I have now in project Center is the same it’s just I switched to text instead of graphics as graphics wasn’t working.
Jun 28, 2022
ThePM-CA --
It would really help us to troubleshoot your graphical indicators criteria if you could share the formula you are using and the graphical indicator criteria you are attempting to use. I would suspect your graphical indicator criteria are not correctly written, but I could be wrong. Please share these with us. Thanks!
It would really help us to troubleshoot your graphical indicators criteria if you could share the formula you are using and the graphical indicator criteria you are attempting to use. I would suspect your graphical indicator criteria are not correctly written, but I could be wrong. Please share these with us. Thanks!
- ThePM-CAJun 28, 2022Brass ContributorI created a lookup table and a custom field called project status the lookup table is projectststus. I have assigned the lookup table to the field
Entity type is project and type is text
Values to display is set to data if I turn to graphical indicators nothing is displayed
Thanks- Paul_MatherJun 28, 2022MVP
ThePM-CA can you paste a screenshot of the lookup table values and the the graphical indicator config on the field?
Paul
- ThePM-CAJun 28, 2022Brass Contributor