Forum Discussion
ThePM-CA
Jun 27, 2022Brass Contributor
Project health indicators
Hi I am kind of struggling displaying graphics as project health indicators. I am able to display text without any problem. I have tried all steps to display icons but in vain I am the proj...
Paul_Mather
Jun 28, 2022MVP
Hello ThePM-CA ,
This guide might help you getting started: https://pwmather.wordpress.com/2014/01/17/getting-started-with-projectonline-part-2-ps2013-office365-project-ppm-sharepointonline-pm/
Paul
ThePM-CA
Jun 28, 2022Brass Contributor
Thank you Paul. I will certainly go through this. The text status which I have now in project Center is the same it’s just I switched to text instead of graphics as graphics wasn’t working.
- Jun 28, 2022ThePM-CA --
It would really help us to troubleshoot your graphical indicators criteria if you could share the formula you are using and the graphical indicator criteria you are attempting to use. I would suspect your graphical indicator criteria are not correctly written, but I could be wrong. Please share these with us. Thanks!- ThePM-CAJun 28, 2022Brass ContributorI created a lookup table and a custom field called project status the lookup table is projectststus. I have assigned the lookup table to the field
Entity type is project and type is text
Values to display is set to data if I turn to graphical indicators nothing is displayed
Thanks- Paul_MatherJun 28, 2022MVP
ThePM-CA can you paste a screenshot of the lookup table values and the the graphical indicator config on the field?
Paul