Forum Discussion

biggie1224's avatar
biggie1224
Copper Contributor
Aug 01, 2023
Solved

Project for Web Accelerator different Data verse tables

Hi All,    I have added project for web as an unmanaged solution in our non default environment, the question if i create a separate unmanaged solution, how can i modify it so that any new projects...
  • Domlit's avatar
    Aug 02, 2023
    Why would you want to do this just out of interest? If you do this, you would also have to find a way of editing the project for the web application so that it would pull Projects from another table. you would also have to recreate exactly all the relationships to the other tables (ie tasks are not saved to msdyn_projects, they are saved to msdyn_projecttasks, so you would need to recreate this connection and all the others that contribute to a project in PftW). It would be a considerable undertaking that I don't see much benefit in doing to be honest.

Resources