Project For The Web
Edit: I now realize that instead of cloud based project I shouldn't be referring to it as Project for the Web.
I am a board member for a non profit where we just started using the cloud based version of Project. We did so so that 3 of us could collaborate in real time. Using this version, we are enabled to create no other dependencies other than start to finish. Some of our tasks need to start at the same time and some need to finish at the same time. Has anyone used the cloud based version, and if so, is there a way to create the other types of dependencies?
2 Replies
- jhblakeCopper ContributorIt looks like the December release will have the type of dependencies you are looking for: Advanced Dependencies ~ Set non-default dependencies between tasks such as Start-to-Start, Finish-to-Finish and Start-to-Finish dependencies.
- VPGibbsCopper ContributorHas Microsoft set a release date for an automatic update?