Forum Discussion
Project for the Web Summary Tasks and Buckets
- Mar 27, 2023
Hello barry2099,
All tasks get a bucket value by default when they are created so it's either the default bucket value from your project, if this is the default board it would be "Bucket 1". Or a bucket value was set for this task before it was made a Summary / parent task. The bucket values are just hidden from the UI for summary / parent tasks but the data is kept in the data verse tables, hence you see this data in the report.
Paul
Hello barry2099,
All tasks get a bucket value by default when they are created so it's either the default bucket value from your project, if this is the default board it would be "Bucket 1". Or a bucket value was set for this task before it was made a Summary / parent task. The bucket values are just hidden from the UI for summary / parent tasks but the data is kept in the data verse tables, hence you see this data in the report.
Paul