Project for the Web: Stop team members changing the duration of their tasks...
Hi Team Can you tell me if it possible stop team members changing the duration of their tasks? Many thanks James
- Feb 04, 2021
Hi James_Price ,
Unfortunately not, once a user has edit access to the project for the web project, they have full edit access.
Paul
James_Price
Feb 04, 2021Brass Contributor
Hi Dale
Understood but the problem with view only is that they cannot update progress. Unless I'm missing something 🙂
Cheers
James
Feb 05, 2021
James_Price -- That is exactly why Project for the Web needs a view or page where team members can enter task progress. So, I do understand your need and concern.
- James_PriceFeb 05, 2021Brass Contributor
🙂 Dale_HowardMVP