Forum Discussion
Project for the Web: Stop team members changing the duration of their tasks...
- Feb 04, 2021
Hi James_Price ,
Unfortunately not, once a user has edit access to the project for the web project, they have full edit access.
Paul
James_Price - In addition to Paul's excellent reply, you need to know that if your team members have a Project Plan 1 license, they are allowed to edit the projects in which they are team members, as well as to be able to create and edit their own projects. On the other hand, if the team members DO NOT have a Project Plan 1 license, they are granted "view only" access to the projects in which they are team members, and they CANNOT change anything. So, based on your description, your team members do have a Project Plan 1 license, which means that Paul gave you the correct answer.
If I were you, I would simply ask my team members NOT to make any changes to their projects without involving me in the decision to make the change. Hope this helps.
- James_PriceFeb 04, 2021Brass Contributor
Hi Dale
Understood but the problem with view only is that they cannot update progress. Unless I'm missing something 🙂
Cheers
James
- Feb 05, 2021
James_Price -- That is exactly why Project for the Web needs a view or page where team members can enter task progress. So, I do understand your need and concern.
- James_PriceFeb 05, 2021Brass Contributor
🙂 Dale_HowardMVP