Project for the Web (P4W) Baselines or Due Dates
Hey All, Are baselines or due dates planned for P4W? Do we know when they will be added? Is there a workaround in the meantime? Related question: where does the data for the custom columns ...
vaiderr
Nov 30, 2023Copper Contributor
if you are using BI to report, a novel approach in the interim for this would be at the time of creating a schedule or plan, you just create a second snapshot of your initial plan and tag it as a baseline, its easy enough to overlay these two plans for basic reporting