Forum Discussion

PatrickGrebe's avatar
PatrickGrebe
Tin Contributor
Jan 17, 2022
Solved

Project for the web: Incomplete notes after MPP import

Hello, when we import an exported project (MPP file) with notes on each task into Project for the web, the notes are incomplete.   Note in Project Desktop: Test Note 1 Test Note 2 After import...
  • John-project's avatar
    Jan 17, 2022
    PatrickGrebe,
    I don't use Project for the web but I'm guessing you are running into the same issue as with export of the Notes field from the desktop version of Project. Is the example note you show in the desktop version a two line note on a single task? If so then export of that note will truncate at the first line feed or 255 characters, whichever occurs first. This limitation has existed in Project from day 1 and is still a limitation. For the desktop version, this limitation can be overcome with VBA but I don't believe Project for the web supports VBA.
    John